Linda Crescent Main Drain
Small Scale Capital Program
Client
Melbourne Water
Location
Linda Crescent, Boroondara
Sector
Lining
Type
Design and Construction
Duration
4 Months – February 2020 to May 2020
Key Facts
- The Linda Crescent Main Drain is located under the busy Glenferrie Road in Melbourne. The Manhole is at a busy intersection adjacent to tram tracks,
- The condition assessment report showed the Linda Crescent drain including manholes showed significant deterioration with concrete spalling, delamination, reinforcement corrosion and cracking of walls, and
- Benefits of Geokrete for this project – Remaining service life of the existing drain was taken into consideration while designing the thickness of Geokrete lining, Addresses voids / cracks before and during installation process. Fully Structural Trenchless Liner achieved, small footprint was helpful due to location of this work is at a busy intersection on Glenferrie Road technology is unaffected by size, shape and direction changes.
Background
Further investigation and structural analysis was carried out and the winner of the multi-criteria assessment done on the available methods of rehabilitation was the “GeoKrete Lining System”.
Scope of Service
The key works required under this project comprised of:
- Further investigations required for scoping of works and designing the solution,
- Detailed design, construction methodology, scheduling,
- Strengthening of the deck, repair and reinforcement of walls, new access manhole,
- Decommission existing manhole; reinstate carriageway,
- Stakeholder engagement, and
- Obtaining permits and permissions to access; traffic management.
Safety
- Site specific Work pack created,
- Toolbox meetings held every day and SWMS followed strictly for all activities of work,
- SWMS created for nightworks, manhole inspections, Yarra Trams, Junction Chambers, and
- Procedures followed for Confined Space Entry.
Environment
- Environmental Management Plan implemented to prevent sediment laden water from entering waterways or stormwater drains, and
- Suitable controls implemented to prevent dust leaving worksite.
Stakeholder Engagement
- Key Stakeholders were Boroondada City Council, Vic Roads, Yarra Trams and Melbourne Water, and
- Liaison with all stakeholders for seamless delivery.